Project Schedule
ACTIVITY |
Anticipated Date |
Receive FERC Order |
October 2009 |
Receive other Federal Permit Approvals |
October - December 2009 |
Receive CTDEP Permit Approvals |
October 2009 and April 2010 |
Receive other CT state Permit Approvals |
October 2009 |
Begin E-3 Construction |
April 2010 |
Begin Modifications to Hanover Compressor Station |
June 2010 |
End Construction |
late 2010 |
|
|